Dominion Energy Electric Transmission March 2026 Updates
CHARLOTTESVILLE-GORDONSVILLEProject Purpose: To maintain reliability and support growing energy needs in the area, this project will rebuild approximately 20 miles of transmission line between the Charlottesville and Gordonsville substations. Announced in early February 2026, this project will replace the existing 230 kV single-circuit, wooden H-frame structures with double-circuit 230 kV monopoles. The height of the structures will increase from an average of 56 feet to 116 feet, on average. The use of